North Rumaila 10" broad cut pipeline sectional replacement during NGL shutdown

Completed  

This Project was awarded to AKT in December 2017 by the Basrah Gas Company. AKT Planned and executed successfully a total of four sectional replacement scopes simultaneously using multiple crews within a 3 week pipeline and plant shut down window.

December 1, 2017

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

Project details
Minus buttonPlus button

1.     Pipeline repairs, valve servicing and replacement at the pipeline pig launcher inside the NGL Romaila plant.

2.     Sectional replacement totaling 130 meters at two locations behind old KAZ LPG plant.

3.     Pipeline repairs, valve servicing and replacement at the pipeline pig receiver inside the KAZ NGL plant.

A total of 150meters length of the pipeline was replaced.

The pig traps were removed, all adjoining valves were serviced and reconstructed to allow for future installation of new pig traps.

Valve pits were also constructed at both ends of the pipelines for installation of future emergency shut down valves.

The Project was completed successfully within planned schedule and without incident.